Eclipse conduced a full site investigation in order to determine the proper remediations for the failing slope, determining that SRT panels were most cost-effective way to correct the slide. Our team drove strategically placed piles in locations determined through an engineering analysis and restored the site before project completion.

Project Location

Madison, MS

Client

Federal Highway Administration

Completion Date

January 1, 2023

Contract Value

$2,513,125.00